This page outlines the timeline for the CIS 2008 cycle. The column on the left hand side outlines the specific steps of the project. The column on the right hand side lists the dates associated with each step.
Calendrier de l'ECI 2008 | |
---|---|
Sample sites selected and recruited |
February 2008 - August 2008 |
Ethics Review Committee approval received for instrument and study methodology |
February 2008 |
Pilot testing |
May 2008 - September 2008 |
Data collection instrument finalized |
September 2008 |
Data collection period |
October 1st - December 31st, 2008 |
Data confirmation and entry |
January 2009 - August 2009 |
Data cleaned |
August 2009 - December 2009 |
Data analyzed and preliminary report drafted |
September 2009 - April 2010 |
Last revisions of study report and database |
April 2010 - August 2010 |
Final CIS - 2008 Report released | October 2010 |